Close sidebar

SBI PO Prelim Exam Question

If 3 men can finish their work for 8 days, then how many men are needed to finish their work in 6 days? a) 5 Men b) 4 Men c) 8 Men d) None of these

  • Sweety
  • 20398 Views
  • 381 Answers
381 Answers
Practice Mock Test
sbi po prelim exam